Lower School - March 2026
AMC Construction has completed the roof at the Jenkins Family Lower School office. Interior ceiling work has begun, while the air conditioning system and all bathrooms are substantially complete. The new Green Dot carline received a final layer of asphalt, and the irrigation system and most of the landscaping have been installed. Flooring installation and power activation are scheduled next.
Upper School - March 2026
In the Bodstrom Family Student Union, crews have begun hanging drywall in the first-floor dining area while continuing essential plumbing and electrical work. On the second floor, AMC has started installing ductwork, with drywall installation to follow. At the Stiles-Nicholson Innovation Center, the roof is now watertight. Exterior stucco work is underway, while interior framing and window installation have commenced on the first floor. Additionally, the cement walkways fronting the classrooms and elevator area have been poured.
Lower School - February 2026
Work progressed at the Jenkins Family Lower School Office in Mid-February, where the stucco has been completed while drywall work and low voltage wire-running started inside. Looking ahead, AMC Construction will start exterior painting next week, which will be followed by landscaping and fencing to complete the new carline at Green Dot.
Upper School - February 2026
At the Bodstrom Family Student Union, roof truss work was completed last week, as was the installation of a grease trap for the kitchen. Next week, interior framing will begin, followed by window installations on both floors. At the Stiles-Nicholson Innovation Center, roof trusses were just installed, and the shoring was removed from the balcony walkways. Upcoming work includes contractors waterproofing window openings, followed by window installations in a couple of weeks.
Lower School - January 2026
Over the holiday break, the roof underlayment of the Jenkins Family Lower School Office was installed. Inside, contractors started electrical wiring, ducting and metal framing work. The new Green Dot Carline received asphalt as crews started working on the curbs. The carline is expected to partially open in the coming weeks. Construction is 50% complete.
Upper School - January 2026
Underground storm structures were installed during the holiday break. The structural bridge connecting the Bodstrom Family Student Union to building 5 was erected. Steel beams for the second floor and balcony are also going in. At the Stiles-Nicholson Innovation Center, the second floor is taking shape with a concrete pour scheduled and metal stairs installed. Construction on both of these facilities is 30% complete.
Lower School - December 2025
At the Lower School, a crane was mobilized to set the trusses for the roof of the Jenkins Family Lower School Office. Crews also began grading work on the new Green Dot carline, ensuring the site is precisely leveled in preparation for asphalt. A partial opening of Green Dot is anticipated in January.
Upper School - December 2025
AMC construction continued their progress at the Upper School, highlighted by the successful pouring of the foundations for both the Bodstrom Family Student Union and the Stiles-Nicholson Innovation Center. Beginning at 3:00 a.m., crews coordinated dozens of cement mixers to achieve a continuous, uninterrupted pour.
Lower School - Week of November 17
Work continued on the Jenkins Family Lower School Office and Green Dot Carline as construction crews poured concrete for the foundation slab. Prior to this, contactors had completed the underground plumbing and electrical work. A partial opening of the Green Dot carline is anticipated after Thanksgiving break.Â
Upper School - Week of November 17
At the Upper School, two transformative new facilities are steadily taking shape. AMC Construction recently poured the foundation for the elevator shaft in the Stiles-Nicholson Innovation Center. Meanwhile, underground plumbing and electrical work continue in both the Innovation Center and the Bodstrom Family Student Union. Additionally, we finalized the purchase of new kitchen equipment. This equipment will enable our chefs to prepare freshly cooked meals onsite beginning next school year!
Lower School - November 2025
Upper School - November 2025
Lower School - October 2025
Upper School - October 2025
Lower School - September 2025
Upper School - September 2025
